PMI Project Management Professional (2025 Version) PMP Question # 149 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 149 Topic 15 Discussion

PMP Exam Topic 15 Question 149 Discussion:
Question #: 149
Topic #: 15

A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product.

What should the project manager do first?


A.

Set up a meeting with the product owner to discuss the stakeholder's concern.


B.

Discuss this with the team and review the project requirements documentation.


C.

Set up a meeting with the sponsor to discuss the details of the deliverable.


D.

Discuss this with the team and put the stakeholder's concern in the issue log.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.