PMI Project Management Professional (2025 Version) PMP Question # 149 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 149 Topic 15 Discussion

PMP Exam Topic 15 Question 149 Discussion:
Question #: 149
Topic #: 15

A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email

What should the project manager do?


A.

Contact the sponsor to request direction regarding the communication tool to be used by the project team


B.

Update the communications management plan based on the product owner’s

preferences and distribute to the team


C.

Suggest to the team to start using the communication tool suggested by the product owner


D.

Request the product owner to use email because using another tool will increase the workload


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.