Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 149 Topic 15 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 149 Topic 15 Discussion

PMP Exam Topic 15 Question 149 Discussion:
Question #: 149
Topic #: 15

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?


A.

Move the solution designer to another team.


B.

Review the process that resulted in this situation.


C.

Stop work until the design document is completed.


D.

Ask the team to document the design.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.