Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 196 Topic 20 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 196 Topic 20 Discussion

PMP Exam Topic 20 Question 196 Discussion:
Question #: 196
Topic #: 20

A primary stakeholder is unable to join the project status meetings consistently. The project manager has been communicating with this stakeholder informally and regularly

to ensure that the stakeholder is up to date on the project. However. the project manager has recently resigned and will not be meeting with the new project manager prior to

departure.

How should the project manager ensure that the new project manager continues to update this particular stakeholder?


A.

Update the communications management plan with specific information on stakeholder engagement.


B.

Update the stakeholder engagement plan with the specific communication needs for the stakeholder.


C.

Ensure that the project team has been provided guidance on the specific needs of this stakeholder.


D.

Ensure that the project documents contain specific instructions regarding the stakeholder.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.