New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 58 Topic 6 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 58 Topic 6 Discussion

PMP Exam Topic 6 Question 58 Discussion:
Question #: 58
Topic #: 6

A project manager is leading a diverse global team. The team members disagree about the requirements for a recently approved change request. The conflict among the team members has resulted in low morale and decreased performance.

What should the project manager do?


A.

Allow the most senior team member to make a decision and communicate the decision to the team members.


B.

Speak with the team members about their disagreement and seek clarity regarding the requirements.


C.

Ask for advice from the human resources (HR) department about how to handle the situation.


D.

Escalate to the change control board (CCB) and have them seek clarity on the requirements of the change.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.