PMI Project Management Professional (2025 Version) PMP Question # 58 Topic 6 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 58 Topic 6 Discussion

PMP Exam Topic 6 Question 58 Discussion:
Question #: 58
Topic #: 6

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important

milestone in a week.

What should the project manager do next?


A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.


B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.


C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.


D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.