Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 185 Topic 19 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 185 Topic 19 Discussion

PMP Exam Topic 19 Question 185 Discussion:
Question #: 185
Topic #: 19

During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much

experience in development.

What should the project manager do?


A.

Allow the team to reevaluate the tasks and determine how they should be allocated.


B.

Maintain the same task allocation structure to avoid any disruption in the project team.


C.

Move the developer to another team and look for a replacement developer.


D.

Request that all quality assurance tasks be allocated to the new resource.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.