PMI Project Management Professional (2025 Version) PMP Question # 185 Topic 19 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 185 Topic 19 Discussion

PMP Exam Topic 19 Question 185 Discussion:
Question #: 185
Topic #: 19

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?


A.

Give the new team member time to contribute until they ask for help and support.


B.

Assign the new team member tasks so that the team member knows on what to focus.


C.

Approach the team member to identify any issues and then plan a resolution accordingly.


D.

Review the project with the team member to ensure the project scope is understood


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.