PMI Project Management Professional (2025 Version) PMP Question # 177 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 177 Topic 18 Discussion

PMP Exam Topic 18 Question 177 Discussion:
Question #: 177
Topic #: 18

A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task

What should the project manager do?


A.

Ask the team member to follow the approved communications management plan to communicate their issue


B.

Schedule a meeting with the concerned team member to review and update the issue log together


C.

Review the risk register with the team member to find the proper response action for this issue.


D.

Ask the team member to raise a change request to assess the issue in detail


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.