PMI Project Management Professional (2025 Version) PMP Question # 176 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 176 Topic 18 Discussion

PMP Exam Topic 18 Question 176 Discussion:
Question #: 176
Topic #: 18

During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product's operating procedures.

What should the project manager do?


A.

Provide the team with the enterprise environmental factors (EEFs).


B.

Run a benchmark with similar sites to compare compliance constraints.


C.

Look into lessons learned documentation for similar projects.


D.

Hire a specialized engineer to support the design team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.