New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 176 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 176 Topic 18 Discussion

PMP Exam Topic 18 Question 176 Discussion:
Question #: 176
Topic #: 18

During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific

component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality

management plan and there is no reference to this component.

What should the project manager do next?


A.

Inform the project sponsor of the situation and wait for the sponsor to provide further directions.


B.

Call a technical meeting with the customer to agree on a specification for the component and document it in the quality management plan.


C.

Submit a change request to proceed with the replacement of the component and wait for further customer instructions.


D.

Keep running the manufacturing line because there are no quality specifications for this component.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.