PMI Project Management Professional (2025 Version) PMP Question # 180 Topic 19 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 180 Topic 19 Discussion

PMP Exam Topic 19 Question 180 Discussion:
Question #: 180
Topic #: 19

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)


A.

Create a change request to discuss with the change control board (CCB).


B.

Request additional budget for contingency.


C.

Perform a risk identification process with the project team.


D.

Consult with the project stakeholders.


E.

Discuss the possible impacts with subject matter experts (SMEs).


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.