Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 180 Topic 19 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 180 Topic 19 Discussion

PMP Exam Topic 19 Question 180 Discussion:
Question #: 180
Topic #: 19

In an agile project, the team is disagreeing about which user story to complete first. One is technically complex and long to complete. The second is a lower priority but easy to complete.

What should the project manager do?


A.

Have the team complete the technically complex story first.


B.

Work with the product owner to clarify and prioritize the backlog stories.


C.

Have the team complete the less complex story first.


D.

Work with the agile coach on the user stories to avoid conflict.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.