PMI Project Management Professional (2025 Version) PMP Question # 93 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 93 Topic 10 Discussion

PMP Exam Topic 10 Question 93 Discussion:
Question #: 93
Topic #: 10

A project manager is facilitating meetings with a diverse team, considering that the team members come from different cultures and have different backgrounds. What should the project manager do to facilitate effective communication?


A.

Create incentives to promote better communication among team members.


B.

Assign the work packages based on geographical working groups.


C.

Understand and consider the emotions of each team member.


D.

Plan for communication training workshops for all team members.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.