PMI Project Management Professional (2025 Version) PMP Question # 164 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 164 Topic 17 Discussion

PMP Exam Topic 17 Question 164 Discussion:
Question #: 164
Topic #: 17

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?


A.

Ask the project team to review and modify all of these reports.


B.

Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.


C.

Explain to the stakeholder that these are the approved templates for the reports.


D.

Ensure that the reports comply with the communications management plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.