New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 164 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 164 Topic 17 Discussion

PMP Exam Topic 17 Question 164 Discussion:
Question #: 164
Topic #: 17

An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.

What should the project manager do?


A.

Establish a project schedule


B.

Assign a team leader


C.

Recognize the team's contributions


D.

Establish a team charter


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.