PMI Project Management Professional (2025 Version) PMP Question # 164 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 164 Topic 17 Discussion

PMP Exam Topic 17 Question 164 Discussion:
Question #: 164
Topic #: 17

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch

What should the project manager do to realize benefits?


A.

Add an entry in the risk log


B.

Implement the changes


C.

Review target benefits.


D.

Improve the team's velocity


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.