PMI Project Management Professional (PMBOK 7th Version) PMP Question # 188 Topic 19 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 188 Topic 19 Discussion

PMP Exam Topic 19 Question 188 Discussion:
Question #: 188
Topic #: 19

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?


A.

Delegate most authorities and control the authority by withholding important information.


B.

Delegate certain authorities and control the authority by withholding important information.


C.

Delegate certain authorities and share information to allow fair decision-making.


D.

Delegate most authorities and share information to allow fair decision-making.