Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 187 Topic 19 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 187 Topic 19 Discussion

PMP Exam Topic 19 Question 187 Discussion:
Question #: 187
Topic #: 19

A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.

What should the project manager do to ensure value is delivered quickly?


A.

Plan the project to deliver value incrementally with regular releases.


B.

Request a budget increase to pay the subject matter experts (SMEs) more overtime


C.

Identify tasks that can run in parallel to deliver the project faster.


D.

Ask the project sponsor to provide additional resources to fast track the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.