PMI Project Management Professional (2025 Version) PMP Question # 187 Topic 19 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 187 Topic 19 Discussion

PMP Exam Topic 19 Question 187 Discussion:
Question #: 187
Topic #: 19

A junior team member escalates an issue to the project manager about another

member's interpersonal skills causing the team to be less effective.

What should the project manager do first?


A.

Have the team members resolve the issue on their own.


B.

Highlight the impact of their behavior and motivate the team member to make improvements.


C.

Gather information and find the root cause of the problem.


D.

Document the escalated issue and address it at the end of the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.