PMI Project Management Professional (2025 Version) PMP Question # 190 Topic 20 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 190 Topic 20 Discussion

PMP Exam Topic 20 Question 190 Discussion:
Question #: 190
Topic #: 20

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?


A.

Check with the team to learn what can be done, and consult an expert


B.

Ask the sponsor to close the project and pay the contracted penalty.


C.

Check that this information was documented correctly


D.

Meet with the sponsor to ask for their support


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.