Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 190 Topic 20 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 190 Topic 20 Discussion

PMP Exam Topic 20 Question 190 Discussion:
Question #: 190
Topic #: 20

A project manager prepared a project benefits management plan. Which of the following should be included in this document?


A.

Project requirements, target benefits, issue log, metrics


B.

Target benefits, strategic alignment, time frame for realizing benefits


C.

Strategic alignment, benefits owner, risk register


D.

Target benefits, benefits owner, lessons learned


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.