PMI Project Management Professional (2025 Version) PMP Question # 192 Topic 20 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 192 Topic 20 Discussion

PMP Exam Topic 20 Question 192 Discussion:
Question #: 192
Topic #: 20

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?


A.

Conducted a document review


B.

Confirmed documentation requirements with stakeholders


C.

Updated the project templates


D.

Implemented a new change control policy


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.