A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became
concerned that the product quality will be sacrificed.
What should the project manager do?
A.
Ensure that the customer and the delivery team agree on the definition of done (DoD) in the beginning of the project.
B.
Invite the customer to join the daily standup meetings to better understand the product design and progress.
C.
Ensure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.
D.
Invite the customer to join the regular sprint planning sessions to better understand the project's progress.
Agile methodologies emphasize customer collaboration over contract negotiation and responding to change over following a plan. Regular demonstrations of product features allow for continuous customer feedback, which is integral to agile projects. This practice ensures that the product evolves according to the customer’s needs and maintains quality throughout development123.
[References:, Agile Methodology in Project Management as a Licensed PMP1., Customer Involvement in Agile Development | Atlassian2., Agile Product Management: Pros and Cons & Best Practices - Hotjar3., , , ]