PMP Exam Topic 10 Question 97 Discussion:
Question #: 97
Topic #: 10

A project manager is working in a constantly changing business environment. In order to address this situation, the project manager has decided to use a collaborative leadership style.

Which landscape describes the project environment?


A.

High accountability, little authority


B.

Available resources, bad roadmaps


C.

Good roadmaps, little accountability


D.

Enough authority, insufficient resources