Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 222 Topic 23 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 222 Topic 23 Discussion

PMP Exam Topic 23 Question 222 Discussion:
Question #: 222
Topic #: 23

A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board (CCB).

What should the project manager do now?


A.

Notify the project team about the change request's approval.


B.

Include the new branch of the bridge in the design.


C.

Communicate the decision to the stakeholder who requested the change.


D.

Evaluate the adjustments to the project management plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.