PMI Project Management Professional (2025 Version) PMP Question # 222 Topic 23 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 222 Topic 23 Discussion

PMP Exam Topic 23 Question 222 Discussion:
Question #: 222
Topic #: 23

At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?


A.

Stop the meeting and reschedule for another time with a more concise presentation.


B.

Set up information review sessions before reconvening another approval session.


C.

Get approval and promise to email more information to the stakeholders to clarify the technical details.


D.

Obtain approval as fast as possible and close the meeting.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.