PMI Project Management Professional (2025 Version) PMP Question # 218 Topic 22 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 218 Topic 22 Discussion

PMP Exam Topic 22 Question 218 Discussion:
Question #: 218
Topic #: 22

A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.

Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?


A.

How the quality was managed


B.

How the acceptance criteria were met


C.

How the scope was managed


D.

How the stakeholders were managed


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.