Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 218 Topic 22 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 218 Topic 22 Discussion

PMP Exam Topic 22 Question 218 Discussion:
Question #: 218
Topic #: 22

A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.

What is the project manager doing?


A.

Network diagram


B.

Decomposition


C.

Work breakdown structure (WBS)


D.

Resource leveling


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.