Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 218 Topic 22 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 218 Topic 22 Discussion

PMP Exam Topic 22 Question 218 Discussion:
Question #: 218
Topic #: 22

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?


A.

Request marketing to launch an advertising campaign for the product that is currently in stock.


B.

Update the project management plan, factoring in furloughs of the assembly team to reduce expenses.


C.

Explore if the materials could be supplied locally and obtained on time.


D.

Meet with the engineering team to manufacture the materials in-house.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.