New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 130 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 130 Topic 14 Discussion

PMP Exam Topic 14 Question 130 Discussion:
Question #: 130
Topic #: 14

An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.

How should the facilitator proceed?


A.

Schedule a release planning session.


B.

Set up a lessons learned session from a similar project.


C.

Conduct a product roadmap session with the team.


D.

Hold a team charter discussion.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.