PMI Project Management Professional (2025 Version) PMP Question # 130 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 130 Topic 14 Discussion

PMP Exam Topic 14 Question 130 Discussion:
Question #: 130
Topic #: 14

Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.

Which three actions should the project manager do? (Choose 3)


A.

Stop the project and review the output.


B.

Ask the testers to provide additional information.


C.

Ask the sponsor for assistance and guidance.


D.

Continue with testing according to the plan.


E.

Brainstorm the issue with the project team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.