New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 132 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 132 Topic 14 Discussion

PMP Exam Topic 14 Question 132 Discussion:
Question #: 132
Topic #: 14

Knowledge sharing has been a key priority for a complex technological project with a large number of team members. During the project

execution phase, the project manager receives numerous complaints from all team members that they are overloaded with knowledge-sharing

emails, which contain useful information but are unmanageable due to the high volume.

What should the project manager do to solve this problem?


A.

Establish an unofficial communications method for the team to share knowledge and lessons learned.


B.

Establish a pull communications method to access knowledge repositories and lessons learned.


C.

Establish an interactive communications method between stakeholders to share knowledge and lessons learned.


D.

Establish a push communications method for the team to share knowledge and lessons learned.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.