New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 133 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 133 Topic 14 Discussion

PMP Exam Topic 14 Question 133 Discussion:
Question #: 133
Topic #: 14

A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not

shared properly among the team. This has caused delivery delays and, ultimately, the failure to complete the project.

What is the root cause of this issue?


A.

Lack of team member training on documentation planning


B.

Improper assignment of tasks to team member pairings


C.

Incorrect communication techniques applied during implementation


D.

Team cohesiveness was lost because team members worked in pairs


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.