PMI Project Management Professional (2025 Version) PMP Question # 133 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 133 Topic 14 Discussion

PMP Exam Topic 14 Question 133 Discussion:
Question #: 133
Topic #: 14

An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project

What should the project manager do?


A.

Train the team on the new regulations as requested by management


B.

Get commitment from the team to include all of the required regulations


C.

Ask the project sponsor to add more time to the project.


D.

Share with participants the need to focus only on product functionality


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.