PMI Project Management Professional (2025 Version) PMP Question # 136 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 136 Topic 14 Discussion

PMP Exam Topic 14 Question 136 Discussion:
Question #: 136
Topic #: 14

A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped

What should the project manager do?


A.

Analyze both projects to determine the most effective use of common resources


B.

Use resource optimization to justify requesting more resources for the critical project


C.

Provide schedule optimization training to the project teams to improve their skills.


D.

Apply fast-tracking techniques to compress the schedule of the critical project


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.