PMP Exam Topic 14 Question 136 Discussion:
Question #: 136
Topic #: 14

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?


A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.


B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.


C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,


D.

Check with procurement to see if there is another previously used contractor who can develop the task.