PMP Exam Topic 22 Question 216 Discussion:
Question #: 216
Topic #: 22

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?


A.

Increase the sprint duration to allow the team more time


B.

Prioritize the contents of the backlog and remove some stories


C.

Create a change request to modify the gate review goals


D.

Use the standup meeting to assess impediments and problems