PMI Project Management Professional (2025 Version) PMP Question # 219 Topic 22 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 219 Topic 22 Discussion

PMP Exam Topic 22 Question 219 Discussion:
Question #: 219
Topic #: 22

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?


A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.


B.

Commit to a detailed global plan from the initiation phase.


C.

Get agreement from stakeholders on high-level deliverables and requirements.


D.

Request the project management office (PMO) to review the initial plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.