Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 219 Topic 22 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 219 Topic 22 Discussion

PMP Exam Topic 22 Question 219 Discussion:
Question #: 219
Topic #: 22

While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers. What should the project manager do?


A.

Discuss this with the functional manager and related parties.


B.

Reject the functional manager's change request immediately.


C.

Analyze the impact of the change request on the project.


D.

Apply for a formal change control board (CCB) approval.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.