Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 219 Topic 22 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 219 Topic 22 Discussion

PMP Exam Topic 22 Question 219 Discussion:
Question #: 219
Topic #: 22

A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly

requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes

of a request. Both of them are equal in seniority and both report to the same functional manager.

How should the project manager proceed?


A.

Update the communications management plan and the stakeholder engagement plan.


B.

Escalate the issue to the functional manager and explain the situation to them.


C.

Negotiate a mutually agreeable feedback cycle with acceptable timelines.


D.

Refer the lead project manager to the communications management plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.