PMI Project Management Professional (2025 Version) PMP Question # 220 Topic 23 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 220 Topic 23 Discussion

PMP Exam Topic 23 Question 220 Discussion:
Question #: 220
Topic #: 23

At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting

with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.

What should the project manager do to assess the priorities and meet the new objective?


A.

Submit a change order request with the new project objective to the project management office (PMO).


B.

Initiate a crashing routine to gain extra time for the added feature.


C.

Communicate the results and negotiate the needed resources and time with the stakeholder.


D.

Ask the project team to work overtime in order to accommodate the new changes.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.