Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 182 Topic 19 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 182 Topic 19 Discussion

PMP Exam Topic 19 Question 182 Discussion:
Question #: 182
Topic #: 19

A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.

What should the project manager do next?


A.

Detail the reason for the project delay in the status report.


B.

Invite the stakeholders to discuss a mitigation plan.


C.

Take on some of the necessary work to minimize the impact.


D.

Register an issue and escalate it to the project sponsor.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.