PMI Project Management Professional (2025 Version) PMP Question # 182 Topic 19 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 182 Topic 19 Discussion

PMP Exam Topic 19 Question 182 Discussion:
Question #: 182
Topic #: 19

A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?


A.

Project stakeholders and the team


B.

External subject matter experts (SMEs) and the team


C.

Project sponsor and the team


D.

Project sponsor and the external SMEs