Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?


A.

Discuss the issue with the project sponsor.


B.

Review the resources required for the tasks on the critical path.


C.

Review and update the risk management plan.


D.

Allocate resources to develop the competencies of the other team members