PMI Project Management Professional (PMBOK 7th Version) PMP Question # 181 Topic 19 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 181 Topic 19 Discussion

PMP Exam Topic 19 Question 181 Discussion:
Question #: 181
Topic #: 19

A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.

One particular pain point is the transition to operations, where the issues usually arise.

What should the project manager do to improve this scenario?


A.

Increase the focus on backlog items that cover support requirements, as well as product manuals and operation guides.


B.

Ask the support/operation team to participate in the daily standup meetings to contribute to the project's progress.


C.

Engage the operation teams in the retrospectives and demo sessions and incorporate their feedback on project activities.


D.

Foster stakeholder participation by engaging them early on the backlog discussions.