Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 223 Topic 23 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 223 Topic 23 Discussion

PMP Exam Topic 23 Question 223 Discussion:
Question #: 223
Topic #: 23

A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.

How should the project manager handle this situation?


A.

Inform the human resource (HR) department about the issue.


B.

Allow the project team to discuss the problem with this team member.


C.

Discuss the issue with the team member's functional manager.


D.

Speak to the team member regarding the need to improve performance.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.