PMP Exam Topic 23 Question 223 Discussion:
Question #: 223
Topic #: 23

A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce

the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December

might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.

What should the project manager do about this risk?


A.

Update the risk register and take advantage of the opportunity.


B.

Review the supplier's contract to understand the terms of sale.


C.

Accept the risk and update the risk register.


D.

Insist that the supplier deliver the goods on the agreed date.