PMI Project Management Professional (2025 Version) PMP Question # 223 Topic 23 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 223 Topic 23 Discussion

PMP Exam Topic 23 Question 223 Discussion:
Question #: 223
Topic #: 23

The project manager has recently received funding approval for a training program

for the entire project team but has not yet defined the most effective training course. One

team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?


A.

Send this change request to the change control board (CCB) for approval.


B.

Approve the request for the specialized training.


C.

Reject the request as it does not impact the project deliverables.


D.

Validate if the training is within scope and budget.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.