New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 160 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 160 Topic 17 Discussion

PMP Exam Topic 17 Question 160 Discussion:
Question #: 160
Topic #: 17

A project manager is assigned to a global project with dispersed team members. Previously, when working with remote teams, the project manager observed that team members do not tend to produce quality work.

What should the project manager do to ensure the project is completed on time with quality?


A.

Encourage the team to participate in a peer evaluation activity by the end of the project.


B.

Introduce the use of time sheets and ask team members to review and submit them regularly.


C.

Arrange regular team meetings for the team to update one another on the progress of their assigned tasks.


D.

Meet with the team together and in one-on-one meetings to set clear, shared targets.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.