PMI Project Management Professional (2025 Version) PMP Question # 160 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 160 Topic 17 Discussion

PMP Exam Topic 17 Question 160 Discussion:
Question #: 160
Topic #: 17

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.

What should the new project manager do to address the process improvements?


A.

Understand the context and interdependencies of the process from the team members and then define improvements


B.

Continue with the process as is. and wait until the next phase to suggest any improvements


C.

Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework


D.

Define a ground rule to comply with the quality standard and ask the team members to apply it.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.