PMI Project Management Professional (2025 Version) PMP Question # 160 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 160 Topic 17 Discussion

PMP Exam Topic 17 Question 160 Discussion:
Question #: 160
Topic #: 17

A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.

What should the project manager do first?


A.

Register a new risk in the risk management plan.


B.

Ask for additional resources and review the project estimate.


C.

Review organizational process assets (OPAs) and perform analogous estimating.


D.

Complete a bottom-up estimation for the project activities.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.