PMI Project Management Professional (2025 Version) PMP Question # 252 Topic 26 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 252 Topic 26 Discussion

PMP Exam Topic 26 Question 252 Discussion:
Question #: 252
Topic #: 26

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?


A.

Accommodate the change request to serve the client's needs


B.

Consult with team members and allow them to make a decision


C.

Convince the client not to make changes to the project


D.

Make transactional decisions focusing on the project goals


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.