Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 251 Topic 26 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 251 Topic 26 Discussion

PMP Exam Topic 26 Question 251 Discussion:
Question #: 251
Topic #: 26

A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)


A.

Schedule regular meetings with the key stakeholder to provide updates and receive feedback,


B.

Share weekly status reports with detailed information about the project and team performance.


C.

Submit performance reports and task assignments to keep the stakeholder informed.


D.

Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders.


E.

Provide training to the team on emotional intelligence and status reporting techniques.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.