PMI Project Management Professional (2025 Version) PMP Question # 255 Topic 26 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 255 Topic 26 Discussion

PMP Exam Topic 26 Question 255 Discussion:
Question #: 255
Topic #: 26

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?


A.

Create an entry in the impediment board and assign it.


B.

Invite the project team to a swarming session to define a solution


C.

Leverage the network of the former department and ask for help


D.

Escalate the issue to the product owner to define the next steps


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.