PMI Project Management Professional (2025 Version) PMP Question # 256 Topic 26 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 256 Topic 26 Discussion

PMP Exam Topic 26 Question 256 Discussion:
Question #: 256
Topic #: 26

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?


A.

Allow the team to make decisions to stay on schedule.


B.

Postpone the vacation to a different time.


C.

Ask the project sponsor to make any necessary decisions.


D.

Analyze the impacts and create a plan for team decision making


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.