PMI Project Management Professional (2025 Version) PMP Question # 86 Topic 9 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 86 Topic 9 Discussion

PMP Exam Topic 9 Question 86 Discussion:
Question #: 86
Topic #: 9

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?


A.

Ensure the stakeholder engagement plan is accurate and properly documented.


B.

Review the lessons learned from the previous project


C.

Identify the risk of implementing the new solution and evaluate the impact on the project.


D.

Create a lessons learned document for the initiation phase


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.