PMI Project Management Professional (2025 Version) PMP Question # 86 Topic 9 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 86 Topic 9 Discussion

PMP Exam Topic 9 Question 86 Discussion:
Question #: 86
Topic #: 9

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are

being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting

market requirements.

What should the project manager do?


A.

Continue the iteration and add the requested changes.


B.

Continue the iteration and review the change with the customer.


C.

Cancel the iteration and meet with the product owner.


D.

Cancel the iteration and add the requested changes.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.