New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 86 Topic 9 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 86 Topic 9 Discussion

PMP Exam Topic 9 Question 86 Discussion:
Question #: 86
Topic #: 9

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.

What should the project manager do?


A.

Assess the schedule impact and evaluate the most feasible solution to keep the project on track.


B.

Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.


C.

Initiate regular conference calls with the vendor for status updates to keep this item in focus.


D.

Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.