Question #: 87
Topic #: 9

A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.

How should the project manager continually evaluate the effectiveness of the virtual team's engagement?


A.

Collect feedback from the team to discuss alternatives to enhance the communication.


B.

Conduct individual meetings to create a trusting environment with team members.


C.

Establish periodic face-to-face meetings and address the communication topic.


D.

Hold meetings in accordance with the team members’ preferences and availability.