Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 257 Topic 26 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 257 Topic 26 Discussion

PMP Exam Topic 26 Question 257 Discussion:
Question #: 257
Topic #: 26

A project manager is working with several junior engineers on a project. The project manager noticed that when the junior engineers are asked questions, they defer te more senior team members on the team for answers. Having worked with the junior engineers on another project, the project manager knows they are capable of making these minor decisions correctly.

This uncertainty from the junior engineers is now slowing progress.

‘What should the project manager do?


A.

Update the risk register to reflect the possible impact of the projects slower progress,


B.

Ensure the junior engineers make decisions within a certain responsibility level and commit to it,


C.

Remove the junior engineers from any decision-making activity until further trained.


D.

Pair senior engineers to shadow the junior engineers and correct them throughout.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.