New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 172 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 172 Topic 18 Discussion

PMP Exam Topic 18 Question 172 Discussion:
Question #: 172
Topic #: 18

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)


A.

Requirements analysis


B.

Retrospective


C.

Sprint planning


D.

Standup


E.

Backlog refinement


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.