PMI Project Management Professional (2025 Version) PMP Question # 168 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 168 Topic 17 Discussion

PMP Exam Topic 17 Question 168 Discussion:
Question #: 168
Topic #: 17

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?


A.

Issue log


B.

Project management plan


C.

Risk management plan


D.

Risk register


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.