PMI Project Management Professional (2025 Version) PMP Question # 171 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 171 Topic 18 Discussion

PMP Exam Topic 18 Question 171 Discussion:
Question #: 171
Topic #: 18

In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?


A.

Give the change to the scrum master to investigate how much additional effort the change will require.


B.

Tell the customer that the requirement change will be put into the next project phase if management approves.


C.

Validate the requirement change with the product owner and development team before redefining the scope.


D.

Escalate to management for approval since the change was not included in the original requirements.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.