PMI Project Management Professional (2025 Version) PMP Question # 171 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 171 Topic 18 Discussion

PMP Exam Topic 18 Question 171 Discussion:
Question #: 171
Topic #: 18

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style

What should the project manager do?


A.

Review the set of responsibilities with the team member


B.

Avoid the team member to prevent further conflicts


C.

Escalate the situation to the project sponsor


D.

Review the personnel skill documents


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.