PMI Project Management Professional (2025 Version) PMP Question # 169 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 169 Topic 17 Discussion

PMP Exam Topic 17 Question 169 Discussion:
Question #: 169
Topic #: 17

A project manager is managing a project in the execution phase, which was agreed upon with the sponsor. However, the sponsor is constantly micromanaging and requesting iterations that are affecting the team's effectiveness. The sponsor indicates that as long as the project scope is not affected, these iterations are needed to simplify the project.

How should the project manager handle the situation?


A.

Review validation and control procedures.


B.

Discuss reducing interruptions with the sponsor.


C.

Perform stakeholder requirements activities.


D.

Approach the sponsor about using an agile approach.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.