Question #: 205
Topic #: 21

A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying

resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.

What should the project manager do first?


A.

Reschedule the project taking this new information into account.


B.

Refer to the project's resource management plan.


C.

Ask the project sponsor for external resources.


D.

Create a change request to be validated by the project sponsor.