Questions # 401:

In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.

What should the project manager do next1?

Options:

A.

Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder


B.

Inform the project sponsor that there are stakeholders who are not included in the communications management plan


C.

Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan


D.

Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.


Expert Solution
Questions # 402:

A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase

How should the business increase the value of the project?

Options:

A.

Quantify the expected tangible and intangible benefits in the benefits management plan for each phase


B.

Ask the benefits owner to reassess the identified risks that are impacting the outcomes of the financial benefits.


C.

Consult with experts on methods to reduce costs and increase the financial value of the project


D.

Use a fishbone diagram to find the root cause of the lower financial benefits with the benefits owner


Expert Solution
Questions # 403:

A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches

What should the project manager do about the development team's request"?

Options:

A.

Escalate the request for additional financial resources


B.

Forward the request to the project management office (PMO) to amend the organizational process assets


C.

Ask the project sponsor to obtain approval for implementation of the new approach


D.

Analyze the requirements that will need to be addressed under the requested method


Expert Solution
Questions # 404:

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.

What should the project manager do?

Options:

A.

Ask the human resources director to appoint a senior team leader


B.

Inform the project sponsor about the possible delay


C.

Directly manage the project team to avoid project delays


D.

Provide mentoring to the newly appointed team leader


Expert Solution
Questions # 405:

A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.

Which two actions should the team take to engage this new team member? (Choose two)

Options:

A.

Revisit the team's discussion on team behaviors and norms


B.

Report to the project manager about the new team member’s behavior


C.

Coach the new team member to improve engagement with the team.


D.

Force the new team member to participate in activities that are considered easy


E.

Facilitate an open discussion on all ideas and perspectives


Expert Solution
Questions # 406:

Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings

What should the project manager do?

Options:

A.

Schedule a meeting for the project team to review the communications management plan.


B.

Tell the rest of the project team to continue discussions with the new team member


C.

Send an email to the project team outlining the communications strategy.


D.

Mentor the new team member on the methodology the project team is using


Expert Solution
Questions # 407:

An agile project team is looking to develop quality standards for a project How should the project manager coach the team?

Options:

A.

Determine the tools and techniques suitable for the project and ensure that testing is done early and continuously.


B.

Inform the team that user acceptance testing is required to ensure that the product owner accepts the solution


C.

Insist that test-driven development is implemented along with the automated testing


D.

Ensure that the definition of done (DoD) is provided when the product owner agrees that all acceptance criteria have been met for the user story


Expert Solution
Questions # 408:

The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible

What three actions should the project manager take to address this situation? (Choose three)

Options:

A.

Define team ground rules


B.

Perform a retrospective session


C.

Implement daily team meetings.


D.

Request a manager performance review


E.

Conduct an annual review.


Expert Solution
Questions # 409:

A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months What should the project lead do next?

Options:

A.

Schedule meetings with the customer to determine their ability to support multiple incremental deliveries


B.

Work with the agile team to schedule the incremental deliveries to enable deliveryof business value sooner to the customer.


C.

Work with the stakeholder to understand what the concerns are while at the same time conveying the benefits of incremental deliveries


D.

Provide details of the concern to the agile team and adjust their goals and release plans to conform to the stakeholder's request.


Expert Solution
Questions # 410:

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed

Which two actions should the project manager take? (Choose two)

Options:

A.

Convince the customer to leave the second milestone in place and not change it.


B.

Escalate the issue to upper management to resolve the problem and suggest a plan.


C.

Go back to the development team and discuss which second milestone requirements can be performed in the first quarter.


D.

Ask the customer for their priorities regarding the requirements for the second milestone


E.

Tell the customer that moving the milestone has a very high impact on the cost of the project


Expert Solution
Questions # 411:

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?

Options:

A.

Raise the issues in the retrospective and propose solutions


B.

Inform management that commitments will not be met.


C.

Involve management to help resolve the conflicts


D.

Coach the team both as a whole and individually


Expert Solution
Questions # 412:

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)

Options:

A.

Risk steering committee


B.

Functional managers


C.

Board of directors


D.

Advisory team panel


E.

Chief executive officer


Expert Solution
Questions # 413:

A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected

What should the project manager do going forward?

Options:

A.

Allocate extra time to inspect deliveries for quality assurance upon arrival at the site


B.

Review the contract requirements and ask for the applicable evidence for quality assurance


C.

Have the vendor issue the quality documentation prior to the next delivery.


D.

Call the vendor and have them verbally guarantee the quality of the next site delivery


Expert Solution
Questions # 414:

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?

Options:

A.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones


B.

Create a reward system granting incentives to the team members who are able to catch more defects


C.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.


D.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems


Expert Solution
Questions # 415:

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change

What should the project manager have done to avoid this situation?

Options:

A.

Requested that the sponsor approved the change request first.


B.

Assessed the change's overall impact to the project before submission


C.

Ensured that the change request was aligned with the project scope


D.

Submitted the change request directly to the CCB


Expert Solution
Questions # 416:

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?

Options:

A.

Check the approved list of requirements to see if there are any missing items.


B.

Work with the stakeholder to improve the requirements' acceptance criteria


C.

Review the requirements traceability matrix with the concerned stakeholder


D.

Discuss with the stakeholder which additional requirements should be added


Expert Solution
Questions # 417:

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

Options:

A.

Perform a risk assessment and define a risk response action plan.


B.

Proceed with the project using management reserves to cover any delays or losses.


C.

Propose a pause in this phase to save labor costs and asset depreciation.


D.

Establish new partnerships with other suppliers in anticipation of any delays.


Expert Solution
Questions # 418:

During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client

Match the scenario on the left with the action on the right.

Question # 418


Expert Solution
Questions # 419:

During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project

What should the project manager do?

Options:

A.

Monitor the project sponsor but understand that it is normal to spend more money in the design phase of a project.


B.

Stop crashing the schedule


C.

Manage the project sponsor closely and revise the project's resource management plan to improve indicators


D.

Use a resource-levelling technique


Expert Solution
Questions # 420:

Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects

How should a project manager solve this issue?

Options:

A.

Propose implementing a new project management information system (PMIS).


B.

Request a meeting with senior management to escalate the situation


C.

Promote adoption of the communications management plan with the project team.


D.

Host a team-building event to develop team cohesion and improve communication


Expert Solution
Questions # 421:

A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented

What should the project manager do?

Options:

A.

Prepare a change request and seek approval from the steering committee regarding the new project framework


B.

Conduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan


C.

Bring in a third party company to develop and implement a hybrid framework for this specific project.


D.

Recommend to the PMO that it is not the right time to start implementing adaptive tools in projects


Expert Solution
Questions # 422:

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

Options:

A.

Escalate the matter to the executive board so they can decide on next steps


B.

Prioritize the project backlog and ask the development team to fix the issues


C.

Review the project's benefits management plan with the product owner.


D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits


Expert Solution
Questions # 423:

In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.

What should the project manager do?

Options:

A.

Let the developers focus on the refactoring work and discuss it in the retrospective


B.

Restate to the developers the importance of focusing and meeting the sprint goal.


C.

Praise the developers for their proactivity and focus on quality.


D.

Escalate the issue to the developers’ functional managers


Expert Solution
Questions # 424:

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

Options:

A.

The updated benefits management plan


B.

The updated scope management plan


C.

The updated project management plan


D.

The updated communications management plan


Expert Solution
Questions # 425:

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid

What should the project manager do?

Options:

A.

Add nonpayment to the issue log and keep tracking payments


B.

Hold a meeting with the client to address the issue


C.

Review past projects for payment-related lessons learned


D.

Conduct a meeting with the project team to update the procurement management plan


Expert Solution
Questions # 426:

A company has decided to implement a new archiving system A data breach occurred during the implementation of the project

What should the project manager do first?

Options:

A.

Implement the planned risk response to handle the issue.


B.

Review possible alternative documentation methods with team


C.

Update the risk register with the risk and proposed impact.


D.

Ask the team to fix the system to resolve the issue


Expert Solution
Questions # 427:

A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.

What should the project manager do?

Options:

A.

Speak with peers about the need for a project charter


B.

Develop the project charter and send it for approval


C.

Explain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities


D.

Agree that the project does not require a project charter, especially since the deliverables and milestones are included in the project management plan


Expert Solution
Questions # 428:

A company just started managing a project using an agile approach Due to this change the general manager is worried about the scope definition process for upcoming projects

What should the project manager do to ensure the project scope is completely defined?

Options:

A.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk.


B.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements


C.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations


D.

Ask the general manager to review every requirement to ensure all projects will deliver the requested products


Expert Solution
Questions # 429:

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?

Options:

A.

The project charter and scope statement


B.

The requirements traceability matrix


C.

The business requirement documents (BRD)


D.

The WBS dictionary


Expert Solution
Questions # 430:

The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.

What does that project manager need to do to make the team work in a collaborative way?

Options:

A.

Request the project management office (PMO) for a team of mentors.


B.

Allocate time to mentor the team.


C.

Update the issue log.


D.

Identify any training gaps


Expert Solution
Questions # 431:

A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?

Options:

A.

Update the quality management plan for the overall project


B.

Ask the client to verify and accept the tasks that have been completed


C.

Close out the project tasks that have been completed


D.

Update the communications management plan for the overall project


Expert Solution
Questions # 432:

During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work The project manager figures out that it is due to a technical issue.

What should the project manager do to prioritize this critical impediment?

Options:

A.

Solve the issue for the team member.


B.

Perform a brainstorming session to address the issue and add the solution to the sprint.


C.

Escalate the issue to the software vendor for technical resolution


D.

Coach the team to come up with their own solution and add it to the next sprint


Expert Solution
Questions # 433:

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?

Options:

A.

Revisit the communications management plan and make necessary adjustments


B.

Revisit the scope management plan and note this as a risk


C.

Schedule a meeting with the product owner and finance team to agree on course corrections


D.

Continue developing based on the project management plan and address the issue post delivery


Expert Solution
Questions # 434:

A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support

What approach should the project manager take?

Options:

A.

Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project


B.

Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs


C.

Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk.


D.

Host a project team meeting, then update the risk register and the project management plan


Expert Solution
Questions # 435:

According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right

Question # 435


Expert Solution
Questions # 436:

A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?

Options:

A.

Start developing a business case.


B.

Start a strengths, weaknesses, opportunities and threats (SWOT).


C.

Engage stakeholders and allocate resources


D.

Gather requirements from stakeholders


Expert Solution
Questions # 437:

A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?

Options:

A.

Review the milestone list to determine which tasks can be fast-tracked


B.

Review the risk management plan to identify the response strategy


C.

Escalate the issue to the sponsor and debrief them about the situation


D.

Organize a team meeting to discuss the next course of action


Expert Solution
Questions # 438:

In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.

What should the project manager calculate to address this critical budgetary situation? (Choose two)

Options:

A.

Contingency control in the project and rebaseline


B.

Mitigation control in the project


C.

Benefits management control in the project


D.

Integrated change control in the project


E.

Currency exchange rate


Expert Solution
Questions # 439:

A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?

Options:

A.

Update the issue log and escalate to the project sponsor


B.

Identify the lack of information as a risk and update the risk register


C.

Schedule more frequent meetings with the technical manager.


D.

Review and update the stakeholder engagement plan


Expert Solution
Questions # 440:

At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?

Options:

A.

Project audit


B.

Lessons learned


C.

Organizational process assets


D.

Procurement audit


Expert Solution
Questions # 441:

Drag the characteristics of the stage on the left to the correct Tuckman Ladder stage on the right

Question # 441


Expert Solution
Questions # 442:

A project manager finished reviewing the project deliverables for the current iteration with the customer A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated

What should the project manager do to address this issue?

Options:

A.

Create a change request and update the scope management plan


B.

Conduct stakeholder identification and a project objectives review session


C.

Update the stakeholder list and fix the deliverables


D.

Update the project management plan and lessons learned


Expert Solution
Questions # 443:

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

Options:

A.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables


B.

Request more funding from the project sponsor to hire additional skilled resourcesand to incorporate additional quality in the project delivery approach and outcome


C.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions


D.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives


Expert Solution
Questions # 444:

The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable

What personality indicators should the project manager consider when determining what communication style to use with this team member?

Question # 444


Expert Solution
Questions # 445:

After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features

What should the project manager do to avoid this in the future?

Options:

A.

Set up requirements-gathering sessions with all key stakeholders to evaluate the scope once again and reprioritize the backlog based on the sessions.


B.

Schedule adequate sprint demos to gather early feedback from the stakeholders and adapt the plan accordingly


C.

Incorporate design thinking practices into the project life cycle to better understand the product's personas and be more effective to match their needs.


D.

Evaluate the team's skills to look for someone with experience in product design and assign that person the task of rebuilding the product interface


Expert Solution
Questions # 446:

A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.

Which action should the project manager take to improve the team's performance?

Options:

A.

Set up a training session for all project team members


B.

Reach out to the functional managers for support


C.

Speak individually with each project team member about making the needed updates


D.

Send an email asking all project team members to complete updates at the end of the day


Expert Solution
Questions # 447:

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?

Options:

A.

Reduce the priority of project risks as all remaining risks are low-level


B.

Notify stakeholders that all high-level risks have been resolved


C.

Reevaluate identified risks and update the risk register


D.

Reclassify low-level risks as high-level risks


Expert Solution
Questions # 448:

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

Options:

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs


B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team


C.

The project manager should allow the resources to periodically choose on which team they would like to work.


D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization


Expert Solution
Questions # 449:

A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?

Options:

A.

The contract has not been appropriately reviewed by the project team


B.

The stakeholder engagement plan has not been correctly implemented


C.

The legal department has not disseminated the law correctly to all staff.


D.

The project manager does not have enough knowledge on this legal matter


Expert Solution
Questions # 450:

A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right

Question # 450


Expert Solution