Questions # 401:

During project execution, an important stakeholder threatens to withdraw support

for the project, citing a lack of transparency and accountability in the way the project is being

executed. What should the project manager do to handle this situation?

Options:

A.

Approach the stakeholder to address the concerns.


B.

Consult the risk management plan.


C.

Escalate the issue to the project management office (PMO).


D.

Refer the stakeholder to the project sponsor.


Expert Solution
Questions # 402:

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

Options:

A.

Manage the scope baseline to influence the factors that drive change.


B.

Follow the proper change control process and evaluate the change for further impact.


C.

Work with the customer to ensure the feature adds value.


D.

Perform frequent reviews with the customer to ensure that the product is working as

expected.


Expert Solution
Questions # 403:

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items

What should the project manager do as a servant leader?

Options:

A.

Ask the sponsor to submit a change request to the change control board (CCB)


B.

Support the product owners decision to change the priority of the product backlog items


C.

Accept the request and include the product backlog items in the next sprint


D.

Review the impact of the change on the schedule management plan baseline


Expert Solution
Questions # 404:

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

Options:

A.

Develop requirements and designs to support a faster product release.


B.

Emphasize the adoption of a predictive approach to minimize ambiguity.


C.

Recommend an agile approach so the project can be delivered iteratively.


D.

Outsource development of the product to a third party with more experience.


Expert Solution
Questions # 405:

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?

Options:

A.

Ask the issue reporter to close the issues, because there are no project team members

who have the required domain knowledge.


B.

Review the open issues with the issue reporter and issue a change request to hire an

external domain expert.


C.

Request that the project team members learn the required domain knowledge and

resolve the open issues in a short time.


D.

Reduce the project scope to ensure that the project team has the knowledge to deliver

the system on schedule.


Expert Solution
Questions # 406:

A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?

Options:

A.

Modeling directive leadership


B.

Modeling commanding leadership


C.

Modeling adaptive leadership


D.

Modeling servant leadership


Expert Solution
Questions # 407:

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule

What should the project manager do?

Options:

A.

Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively


B.

Escalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training


C.

Make sure all stakeholders have access to the system and know where to find project artifacts


D.

Send the project schedule via email to the stakeholders who need that information


Expert Solution
Questions # 408:

A project manager has been assigned lo an important agile project During protect execution, a vendor was approved to produce the project deliverables. What should the project manager do to ensure project continuity between the vendor and the team?

Options:

A.

Request that the vendor provides a manual with all required knowledge


B.

Implement retrospectives with the vendor to gather the required knowledge


C.

Submit a change request to extend the vendor's contract to provide formal training for the team


D.

Conduct daily knowledge transfer standups to ensure that the team is properly trained


Expert Solution
Questions # 409:

A project sponsor asks the project manager to explore a hybrid approach for a new

project. The product manager for this project has already prepared a detailed specification for the product.

What should the project manager do to proceed with the project management plan?

Options:

A.

Ask the team to assess whether the product specification can be expressed in user

stories to enable a Scrum or Kanban approach.


B.

Explore with the product manager to determine if there are viable opportunities to

deliver value incrementally and increase business value.


C.

Recommend to the project sponsor that a predictive approach is appropriate for the

project due to the stable product requirements.


D.

Ask the product manager whether they are prepared to act as product owner for the

project in order to participate in iterative planning and reviews.


Expert Solution
Questions # 410:

An organization is adopting an agile mindset. On the first agile project, the project

manager faced an issue because the team was unable to make decisions on time.

What should the project manager do to address the problem?

Options:

A.

Define clear guidelines on how decisions should be made under the new

organizational policy and reinforce them with the team on every occasion.


B.

Invite senior leadership to a team-building workshop and restate the importance of

accountability and leadership under the new company direction.


C.

Assess the situation to understand how the organization's culture impacts the decisionmaking process, and coach the team toward a new model.


D.

Adopt an autocratic leadership style and dictate all decisions in order to speed up the

team's velocity.


Expert Solution
Questions # 411:

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

Options:

A.

Increase the overall project duration to account for the inexperienced team members

on the project.


B.

Ensure planning has accounted for replacing team members in new project roles who

do not deliver on project goals.


C.

Assess the training requirements and ensure time for professional development

training by senior members.


D.

Revisit the project resource allocation to remove the inexperienced team members

assigned to the project.


Expert Solution
Questions # 412:

When a project manager is trying to determine a leadership style to use on a project what should they consider?

Options:

A.

Number of tasks on the protect


B.

Culture of the organization


C.

Project timeline


D.

Experience of the project manager


Expert Solution
Questions # 413:

A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?

Options:

A.

Follow the risk response plan


B.

Use the contingency fund


C.

Prepare a change request


D.

Update the risk register


Expert Solution
Questions # 414:

During the execution of a construction project, the project sponsor asks to make

changes to the floor plan by adding a minimal storage room. The sponsor insists on making

this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?

Options:

A.

Change management plan


B.

Schedule management plan


C.

Scope management plan


D.

Cost management plan


Expert Solution
Questions # 415:

A project requires testing of the final product to be done at another department's

testing facility, which is known for having low availability. This situation could potentially

impact the project schedule.

What should the project manager do next?

Options:

A.

Update the risk register.


B.

Update the issue log.


C.

Update the lessons learned register.


D.

Update the project schedule.


Expert Solution
Questions # 416:

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

Options:

A.

Product backlog, budget, resource management plan


B.

Budget, minimum viable product (MVP), retrospective notes


C.

Resource management plan, retrospective notes, backlog grooming


D.

Backlog grooming, product backlog, minimum viable product (MVP)


Expert Solution
Questions # 417:

A project is on its sixth iteration out of seven. Select the two points where the team is

performing better than expected. (Choose two.)

Question # 417


Expert Solution
Questions # 418:

A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted

What should the project manager do?

Options:

A.

Request stakeholders who understand the technology.


B.

Recommend a change in technology to senior management.


C.

Plan to conduct informal sessions with the stakeholders.


D.

Include the issue in the Issue log and escalate to senior management.


Expert Solution
Questions # 419:

An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work

What should the project manager do?

Options:

A.

Escalate the situation to the engineer's manager


B.

Request external training for the engineer


C.

Request external training for the engineer and designer


D.

Allow the engineer and designer to cross-train with each other


Expert Solution
Questions # 420:

A new project manager is managing a hybrid project. The project manager wants to be

a servant leader to support the team by removing impediments but is not receiving feedback

from the team about the issues and risks they are facing.

What should the project manager do?

Options:

A.

Implement daily standups where the team can share their impediments, risks, and

issues.


B.

Review the communications management plan and implement changes.


C.

Schedule weekly risk review meetings with the team to review project risks and

concerns.


D.

Distribute a copy of the communications management plan to the scrum master.


Expert Solution
Questions # 421:

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?

Options:

A.

Identify how the proposed changes will benefit the project in relation to the business

case.


B.

Ask for a temporary budget increase to avoid cost overruns.


C.

Keep the team motivated and incentivized to avoid exhaustion from working on a

lengthy project.


D.

Assess the schedule delay and begin implementation to avoid additional lags


Expert Solution
Questions # 422:

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

Question # 422

Options:

A.

Review project cost because the project is over budget and ahead of schedule


B.

Review project schedule and cost because the project is over budget and behind schedule


C.

Review project schedule because the project is under budget and behind schedule


D.

Review project scope because the project is under budget and ahead of schedule


Expert Solution
Questions # 423:

A project manager is working on a highly complex project. During the execution of

the project, the local government changed certain environmental regulations, which could

potentially delay the project.

What immediate action should the project manager take?

Options:

A.

Update the issue log.


B.

Update the project baseline.


C.

Update the risk management plan.


D.

Update the change request log.


Expert Solution
Questions # 424:

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?

Options:

A.

Share unsuccessful results from previous projects with a similar scope


B.

Provide the failed test results along with the agreed-upon acceptance criteria


C.

Show that the acceptance criteria were changed by the vendor without approval.


D.

Document in the risk log that the issues in the system were already identified


Expert Solution
Questions # 425:

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

Options:

A.

Encourage and motivate the team with project incentives


B.

Subdivide the team to handle different aspects of the project


C.

Support the team to find and execute the minimum viable product (MVP)


D.

Organize project execution to satisfy the project sponsor s request


Expert Solution
Questions # 426:

In an ongoing project, stakeholders have been approaching team members for status

reports and changes without consulting the project manager. What should the project

manager do to ensure a successful project?

Options:

A.

Send the project charter to all stakeholders for information.


B.

Send an email to all stakeholders directing them to approach the project manager

directly.


C.

Review the stakeholder engagement plan and inform the stakeholders.


D.

Review the change management plan and ask the change control board (CCB) to be

involved.


Expert Solution
Questions # 427:

A project team is executing a project to replace an existing system with a new one.

A new project manager has been hired and observes that the team consist of professionals

who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

Options:

A.

Request a performance assessment for the team from the functional manager.


B.

Evaluate the current effectiveness of the team and define development needs.


C.

Allow each team member to use their individual strengths for project success.


D.

Assign team member roles and responsibilities based on past experience.


Expert Solution
Questions # 428:

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A's project manager do?

Options:

A.

Allow project B's leader to continue building relationships.


B.

Talk with project B's leader to discuss possible impacts to both projects.


C.

Tell project A's team member to ignore project B's leader.


D.

Ensure project A's team member can finish the work committed to project A.


Expert Solution
Questions # 429:

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

Options:

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal and

external resource requirements.


B.

Commit each team member's time and deliverables and aim for overall project

completion.


C.

Continue the project implementation without the site engineers to ensure the schedule

is maintained.


D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.


Expert Solution
Questions # 430:

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

Options:

A.

Meet with the stakeholder to discuss the impact of the deliverable


B.

Consider the stakeholder as a risk and evaluate possible solutions with the project team


C.

Improve communication with the stakeholder to obtain their assistance in the future


D.

Escalate to the project sponsor due to the political nature of the issue


Expert Solution
Questions # 431:

A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company's CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)

What should the project manager do to control this situation?

Options:

A.

Redefine the communications management plan


B.

Develop an integrated change management plan


C.

Document the risk in the project risk register


D.

Review the scope defined in the project charter


Expert Solution
Questions # 432:

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

Options:

A.

Instruct the team to accommodate the changes to the project


B.

Review the project charter to identify the agreed scope


C.

Negotiate the impact of these changes with the client


D.

Escalate the issue to senior management


Expert Solution
Questions # 433:

A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.

What should the project manager ask the team to do?

Options:

A.

Perform collaborative work that is coordinated by the project manager.


B.

Rely on the expert judgment of the product owner.


C.

Use a market-based strategy.


D.

Engage the project sponsor.


Expert Solution
Questions # 434:

A project manager is assigned to deliver an innovative solution that is part of a

brand new offering. The project manager reviews the request for proposal (RFP) and realizes that key terms are restricted to technical resource assignments. There is also a gap in addressing compliance.

How should the project manager bridge the gap and ensure the project delivers the expected

business value?

Options:

A.

Determine the critical requirements.


B.

Document the risks and mitigations.


C.

Define the project schedule.


D.

Create a project scope statement.


Expert Solution
Questions # 435:

An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.

What should the project manager recommend?

Options:

A.

Ensure the product owner determines the priority based on a product roadmap. release plan, and iteration plan.


B.

Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.


C.

Ask the team to prioritize the high-priority Items based on the release plan and what allows tor testing most effectively.


D.

Discard the current categorization of requirements as high, medium, and low and prioritize numerically.


Expert Solution
Questions # 436:

A project team member has lost enthusiasm and is experiencing low morale for a

project they were once excited about. What should the project manager do?

Options:

A.

Escalate the issue to the team member's functional manager and request a response

as soon as possible.


B.

Meet with the team member to understand what the issues are and to provide support.


C.

Leverage other team members who are contributing and making the project a success.


D.

Have the team member transferred to another project and add other resources to the

project.


Expert Solution
Questions # 437:

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

Options:

A.

Work with the team and others in the network to assess and prioritize the obstacles.


B.

Engage with the external stakeholders and the other division of the organization to

resolve the issues.


C.

Escalate the obstacles to the project sponsor for assistance with resolution.


D.

Determine a change response to identify and resolve the obstacles to move the project

forward.


Expert Solution
Questions # 438:

A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

Options:

A.

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions


B.

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel


C.

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities


D.

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members


Expert Solution
Questions # 439:

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

Options:

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.


B.

Schedule a meeting to discuss recent observations with the team member.


C.

Organize a team-building session with all of the team members.


D.

Consult the resource allocation matrix to see if the team member is still required for the

project.


Expert Solution
Questions # 440:

A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.

What should the project manager do?

Options:

A.

Explain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule


B.

Document who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report


C.

Explain to the project sponsor that they are accountable for tracking benefits realization after project completion


D.

Discuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)


Expert Solution
Questions # 441:

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

Options:

A.

Ask the new product owner to explain the importance of the project.


B.

Email the team a detailed outline of the business requirements.


C.

Review the project charter with the team.


D.

Facilitate a discussion of the vision for the project.


Expert Solution
Questions # 442:

An issue reoccurs six months after a project's go-live date despite being resolved

during the project life cycle. What should the project manager have done in the previous

phase to avoid this issue?

Options:

A.

Ensured the project team documented lessons learned about the issue


B.

Ensured the project team applied a long-term solution for the issue


C.

Asked the project team to conduct more testing with users


D.

Discussed the issue with the stakeholders


Expert Solution
Questions # 443:

A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?

Options:

A.

Projects with the least duration


B.

Projects that maximize the business value


C.

Projects with maximum revenue generation


D.

Projects with the least associated risks


Expert Solution
Questions # 444:

A new project manager has been assigned to an environmental project. After

reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

Options:

A.

Injury or loss incidents could delay project deliverables.


B.

It is imperative that established performance metrics are met.


C.

The project manager is obligated to comply with the project location's regulatory

requirements.


D.

The project manager must follow their employer's organizational process assets

(OPAs).


Expert Solution
Questions # 445:

A protect manager has just finished planning for a project when the client adds a new project team member The project manager Knows that the new team member only works remotely and is not in the main office. In addition, the new team member engages with decisions quickly in a face-to-face environment, but is slow to respond otherwise.

How should the project manager reflect this in their planning?

Options:

A.

Send out recurring onsite project meeting invites to ensure the team member's presence.


B.

Update the project charter to include the new team member for this project.


C.

Monitor the new team member's input to gauge their value to the project.


D.

Include the team member in the stakeholder register and update the communications management plan.


Expert Solution
Questions # 446:

One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.

What should the project manager do?

Options:

A.

Assign this member to facilitate the next meeting to ensure project team collaboration.


B.

Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.


C.

Review and update the project ground rules to make meeting attendance mandatory.


D.

Understand the reason for the team member's absence and encourage them to attend future meetings.


Expert Solution
Questions # 447:

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?

Options:

A.

Perform a qualitative risk analysis and update the risk register.


B.

Submit a change request through the Integrated change control process.


C.

Update the issue log and discuss It in the next steering committee meeting.


D.

Estimate the associated costs and increase the project budget accordingly.


Expert Solution
Questions # 448:

A key project stakeholder does not attend any of the project meetings and is

providing false information that the project team is not delivering on time. What should the

project manager do to address this situation?

Options:

A.

Create a new communication artifact for the key stakeholder.


B.

Email the latest status report to the key stakeholder.


C.

Share the meeting recordings with the key stakeholder.


D.

Discuss communication needs with the key stakeholder.


Expert Solution
Questions # 449:

An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives

What should the project manager do?

Options:

A.

Schedule team-building activities to encourage collaboration among the team


B.

Coach the team members to resolve the gaps in understanding


C.

Conduct a kick-off meeting and communicate the goals and objectives of the project


D.

Continue the meetings and communicate the goals and objectives to resolve the gaps


Expert Solution
Questions # 450:

The change control board (CCB) has approved a change request to add a new

component within a product. The operations manager discovers the change after its approval

and complains that the implementation of the change will cause significant disruption to the

production line.

What should the project manager do first?

Options:

A.

Escalate the issue to the project sponsor, as the decision to add the component brings

many benefits even though it will be disruptive to the production line.


B.

Lead a root cause analysis workshop with the design team to identify the failures that

led to the decision to add a component that was not compatible with the production

line.


C.

Meet with the operations manager to explain the background for the change and

understand the operation manager's concerns about the change.


D.

Formally acknowledge the operation manager's concerns and raise a new risk that the

project may deliver late and over budget due to manufacturing difficulties.


Expert Solution