In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.
What should the project manager do next1?
A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase
How should the business increase the value of the project?
A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches
What should the project manager do about the development team's request"?
During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.
What should the project manager do?
A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.
Which two actions should the team take to engage this new team member? (Choose two)
Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings
What should the project manager do?
An agile project team is looking to develop quality standards for a project How should the project manager coach the team?
The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible
What three actions should the project manager take to address this situation? (Choose three)
A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months What should the project lead do next?
In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed
Which two actions should the project manager take? (Choose two)
A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts
What should the project manager do next?
A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)
A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected
What should the project manager do going forward?
A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?
The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change
What should the project manager have done to avoid this situation?
During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?
A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.
What should the project manager do first to prevent the project from going further off track?
During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client
Match the scenario on the left with the action on the right.

During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project
What should the project manager do?
Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects
How should a project manager solve this issue?
A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented
What should the project manager do?
During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications
The team is confused by the product owner's statement
What should the project manager do when using a hybrid approach?
In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.
What should the project manager do?
During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?
While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid
What should the project manager do?
A company has decided to implement a new archiving system A data breach occurred during the implementation of the project
What should the project manager do first?
A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.
What should the project manager do?
A company just started managing a project using an agile approach Due to this change the general manager is worried about the scope definition process for upcoming projects
What should the project manager do to ensure the project scope is completely defined?
A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing
What should the project manager review?
The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.
What does that project manager need to do to make the team work in a collaborative way?
A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?
During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work The project manager figures out that it is due to a technical issue.
What should the project manager do to prioritize this critical impediment?
During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?
A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support
What approach should the project manager take?
According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right

A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?
A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?
In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.
What should the project manager calculate to address this critical budgetary situation? (Choose two)
A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information
What should the project manager do first to resolve this situation?
At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?
Drag the characteristics of the stage on the left to the correct Tuckman Ladder stage on the right

A project manager finished reviewing the project deliverables for the current iteration with the customer A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated
What should the project manager do to address this issue?
A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings
What is one of the key activities that the project manager should undertake to ensure company success?
The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable
What personality indicators should the project manager consider when determining what communication style to use with this team member?

After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features
What should the project manager do to avoid this in the future?
A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team's performance?
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain
What should the project manager do now?
An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team
What should the project manager do?
A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year
What has happened in this situation?
A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right
