Questions # 401:

A company's project management office (PMO) has started to implement iterative tools A project manager is starting a new project and has identified an opportunity to use the iterative tools One of the senior managers is concerned about this modified framework as it is fairly new to the company

What should the project manager do first?

Options:

A.

Organize individual sessions with the stakeholders to build awareness and trust in the new framework


B.

Look for external training on the new framework to eliminate the risk of low engagement from stakeholders.


C.

Send documentation to the senior manager about the advantages of the new framework


D.

Escalate the senior manager's concern to the project sponsor and distribute the status to the team


Expert Solution
Questions # 402:

A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.

What should the project manager do?

Options:

A.

Proceed with the project without allowing scope creep to occur


B.

Use the contingency funds to provide support for the requested projects


C.

Cancel the project since the stakeholder's request is out of scope


D.

Inform the sponsor and document the request in the stakeholder engagement plan


Expert Solution
Questions # 403:

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

Options:

A.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables


B.

Request more funding from the project sponsor to hire additional skilled resourcesand to incorporate additional quality in the project delivery approach and outcome


C.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions


D.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives


Expert Solution
Questions # 404:

After the project charter's approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term.

What should the project manager do in order to gather the information needed from stakeholders?

Options:

A.

Email, call, or meet with each stakeholder separately to obtain their input


B.

Conduct a meeting to build the project management plan with the stakeholders who are available


C.

Escalate to the project sponsor that not all stakeholders are available for a meeting


D.

Meet with the project management team to build the project management plan before consulting stakeholders


Expert Solution
Questions # 405:

A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time

How should the project manager address this situation?

Options:

A.

Address the lack of performance by coaching the new team member


B.

Discuss options to improve performance with the resource manager


C.

Provide performance feedback as part of the retrospective ceremony.


D.

Request a more efficient replacement resource from the project sponsor


Expert Solution
Questions # 406:

In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.

What should the project manager calculate to address this critical budgetary situation? (Choose two)

Options:

A.

Contingency control in the project and rebaseline


B.

Mitigation control in the project


C.

Benefits management control in the project


D.

Integrated change control in the project


E.

Currency exchange rate


Expert Solution
Questions # 407:

Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable

What should the project manager do next?

Options:

A.

Check the project budget to verify if there is enough contingency reserve


B.

Review the cost management plan to determine how to address this issue


C.

Tell the team members that more equipment is not part of the project's scope.


D.

Submit a change request to increase the budget and buy new equipment


Expert Solution
Questions # 408:

A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?

Options:

A.

Add the new stakeholder to the communications management plan


B.

Share the project status reports with the new stakeholder.


C.

Update the stakeholder engagement plan


D.

Schedule a meeting with the new stakeholder


Expert Solution
Questions # 409:

A project manager is m the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence The project is ahead of schedule and running under budget

Which two actions should the project manager take initially to resolve this problem? (Choose two)

Options:

A.

Check the risk register for a prepared response to a resource being suddenly unavailable.


B.

Check if the team member's activities are sufficiently documented to facilitate handover


C.

Check the project's responsibility assignment matrix (RAM) to determine which activities will be affected


D.

Reassign responsibilities across the remaining members using the available float for training.


E.

Obtain the project sponsors support to replace the team member on leave


Expert Solution
Questions # 410:

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

Options:

A.

Ask the team member to enter this potential schedule delay in the risk register.


B.

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges


C.

Actively listen to the team member and identify ways to support their needs in completing the tasks.


D.

Set up team-building activities with the project team members to reduce tension


Expert Solution
Questions # 411:

An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project

What should the project manager do?

Options:

A.

Train the team on the new regulations as requested by management


B.

Get commitment from the team to include all of the required regulations


C.

Ask the project sponsor to add more time to the project.


D.

Share with participants the need to focus only on product functionality


Expert Solution
Questions # 412:

A project manager for a government organization often deals with stakeholder engagement issues Drag the interpersonal skill the project manager should use on t he left to the correct situation on the right

Question # 412


Expert Solution
Questions # 413:

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.

What should the project manager do?

Options:

A.

Set up a meeting with key stakeholders to clarify requirements


B.

Escalate to the project steering committee and request additional time


C.

Travel to the development team's office to push the schedule


D.

Create prototypes with the development team to confirm requirements


Expert Solution
Questions # 414:

A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch

On what should the project manager focus?

Options:

A.

Ensuring that the team is also focused on the overall change management plan


B.

Determining and aligning performance indicators that will help in assessing successful delivery


C.

Planning for regular project updates to cover the status of critical deliverables


D.

Ensuring that the scope management plan is in place to cover all related objectives


Expert Solution
Questions # 415:

During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.

What two actions should the project manager take to prevent the team from being unqualified? (Choose two)

Options:

A.

Exclude the activities from the roadmap


B.

Encourage working in pairs and knowledge sharing


C.

Teach the entire team the new skill.


D.

Facilitate a training event with an external trainer


E.

Increase the time estimates on the activities that require such abilities


Expert Solution
Questions # 416:

A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company

What should the project manager have the Scrum team do to recover from these issues?

Options:

A.

Review constraints in the ongoing sprint planning and evaluate options for the release plan


B.

Stop the sprint and replan and prioritize the backlog to reduce resource levels


C.

Consult the resource management plan for an appropriate response


D.

Continue with existing sprint plans to ensure some of the scope will be delivered


Expert Solution
Questions # 417:

A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right

Question # 417


Expert Solution
Questions # 418:

The project manager just started leading a project team from which the previous project manager resigned After a quick evaluation of the project it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule

What should the project manager do?

Options:

A.

Conduct a meeting with the project team to discuss and address the sources of disagreement


B.

Inform the stakeholders that the project will be delayed due to previous team management


C.

Crash the project timeline to ensure the project is back on schedule


D.

Issue a change request to extend the project schedule based on identified delays


Expert Solution
Questions # 419:

A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required

How should the project manager assist the product owner?

Options:

A.

Coach the product owner on how to create a product backlog


B.

Encourage the team to subdivide the project tasks


C.

Create a work breakdown structure (WBS) and explain the deliverables to the product owner


D.

Discuss the product owner's responsibilities within the project team


Expert Solution
Questions # 420:

A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)

Options:

A.

Use the project's contingency budget


B.

Create a change request with the scope of the new internal projects.


C.

Influence the client to initiate a new project.


D.

Create a work breakdown structure (WBS) of the new scope with the internal projects


E.

Manage the quality of the delivery


Expert Solution
Questions # 421:

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.

What training should the project manager choose for their team to help with this situation?

Options:

A.

Communication training


B.

Negotiation training


C.

Emotional intelligence training


D.

Agile training.


Expert Solution
Questions # 422:

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

Options:

A.

Escalate the matter to the executive board so they can decide on next steps


B.

Prioritize the project backlog and ask the development team to fix the issues


C.

Review the project's benefits management plan with the product owner.


D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits


Expert Solution
Questions # 423:

One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate

What interpersonal skill did the project manager use?

Options:

A.

Networking


B.

Emotional intelligence


C.

Conflict management


D.

Influencing


Expert Solution
Questions # 424:

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)

Options:

A.

Risk steering committee


B.

Functional managers


C.

Board of directors


D.

Advisory team panel


E.

Chief executive officer


Expert Solution
Questions # 425:

A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline

What two actions should the project manager take'? (Choose two)

Options:

A.

Send letters to the neighbors and ask them kindly not to disturb the project.


B.

Set up a meeting with neighborhood representatives to win their cooperation


C.

Analyze the situation and find out what is causing the neighborhood's negative attitude.


D.

Ask the customer to extend the project deadline to allow time for conflict resolution


E.

Ask the mayor of the city to use their authority to stop neighborhood resistance


Expert Solution
Questions # 426:

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

Options:

A.

Organize a planning session with the development team and use their estimations to complete the schedule.


B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.


C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.


D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.


Expert Solution
Questions # 427:

A newly hired team member just joined the project team and reports directly to the

project manager. In the first week, this new member tells the project manager that there is a

task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?

Options:

A.

Guide the team member on how to resolve the conflict.


B.

Analyze the project schedule and look for alternatives.


C.

Perform crashing and/or fast tracking of the schedule.


D.

Meet the team member and try to plan a course of action together.


Expert Solution
Questions # 428:

A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?

Options:

A.

Ask the project sponsor to replace the contractor since they do not have agile experience


B.

Issue a formal notice to the contractor to obtain an agile certification


C.

Consult the project team to understand the extent of the training needs for the contractor


D.

Instruct the contractor to receive agile training since the project has already started


Expert Solution
Questions # 429:

A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings

What should the project manager do?

Options:

A.

Ask the individual who is hosting the event to use private communication methods.


B.

Set up a meeting with the distracted team member to discuss any issues


C.

Add a social events section to the charter to handle these situations


D.

Ask the individual who is hosting the event to mark it as private


Expert Solution
Questions # 430:

A project manager has been assigned to take over an existing software project. The project manager inherited a lean team comprised of key stakeholders, subject matter experts

(SMEs), and senior developers. While reviewing the project status with the team, the project manager observes that the team seems to lack direction and enthusiasm.

What should the new project manager do?

Options:

A.

Ensure everyone performs their assigned tasks as planned.


B.

Organize frequent team building sessions and update the risk register.


C.

Meet with the project sponsor and propose a corrective action for the project.


D.

Encourage participation in decision making and empower the team.


Expert Solution
Questions # 431:

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

Options:

A.

Escalate the issue to the team's manager.


B.

Remove some of the team members.


C.

Review the roles and responsibilities document.


D.

Develop working agreements with the team.


Expert Solution
Questions # 432:

A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50 The actual expenditure is US$2,000 and 50 user stories have been delivered.

Which statement is true''

Options:

A.

The project is on budget and on schedule.


B.

The project is over budget and behind schedule


C.

The project is under budget and behind schedule.


D.

The project is under budget and on schedule.


Expert Solution
Questions # 433:

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

Options:

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline


B.

Motivate project team members by offering incentives to complete the project on time


C.

Describe to the team members how specific tools and techniques can be used to finish on time


D.

Convince team members to use a specific methodology to complete the project on time


Expert Solution
Questions # 434:

After a project team has been working on a project for several months the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project

How should the project manager handle this situation?

Options:

A.

Comply with the project sponsor's request to not archive the project artifacts.


B.

Consult with the project management office (PMO) for guidance on project artifacts.


C.

Archive the project artifacts on the project manager's local computer for future reference.


D.

Document the project sponsor's instructions as the archived project artifacts.


Expert Solution
Questions # 435:

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

Options:

A.

Initiated requirements planning to analyze, document, and manage requirements


B.

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process


C.

Implemented the change request process to harness change to the stakeholders’ advantage


D.

Used progressive elaboration to enhance the scope management plan with additional details


Expert Solution
Questions # 436:

A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?

Options:

A.

Be clear with directions and assignments so people stay focused and engaged with their work.


B.

Promote an environment where everybody knows what their contribution means to the project as a whole.


C.

Design a reward system to get people motivated by recognizing significant individual contributions from the last sprint


D.

Encourage continuous rotation of roles among team members to keep people motivated throughout project delivery.


Expert Solution
Questions # 437:

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

Options:

A.

Stakeholders are satisfied with the current status.


B.

The project is under budget and on schedule


C.

The project is aligned with the project charter


D.

The protect is aligned with the benefits management plan


Expert Solution
Questions # 438:

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

Options:

A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments


B.

Incremental delivery and frequent backlog refinement based on user feedback


C.

Iterative development and collection of frequent feedback from project team members


D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented


Expert Solution
Questions # 439:

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

Options:

A.

Service level agreement (SLA)


B.

Statement of work (SOW)


C.

Scope management plan


D.

Memorandum of understanding (MOU)


Expert Solution
Questions # 440:

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

Options:

A.

The team with the higher velocity is performing better and should be rewarded.


B.

The issue should be addressed as part of a retrospective in the next iteration.


C.

The velocity should not be compared as teams can size items differently.


D.

The velocity of both teams should be compared at the end of every iteration.


Expert Solution
Questions # 441:

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?

Options:

A.

Ask the team leader to assign other resources.


B.

Update the issue log.


C.

Include this in the risk register.


D.

Escalate the issue to the functional manager.


Expert Solution
Questions # 442:

A project manager was just assigned to a project as the leader of an experienced agile team. How should the project manager influence the team to accomplish the project objectives?

Options:

A.

Express trust in the team's ability to fulfill the necessary deliverables.


B.

Assert judgment over the team.


C.

Use a plan-driven approach in order to demonstrate control over the project.


D.

Increase the amount of subject matter experts (SMEs) to get better results.


Expert Solution
Questions # 443:

A project manager is working with an agile team. A key stakeholder who does not

join the sprint planning session is very unhappy, as the delivery date for the final product has

been pushed back three times. What should the project manager do?

Options:

A.

Meet with the stakeholder to understand the concern and business impact, reprioritize as necessary, and invite them to join the sprint planning session.


B.

Direct the product owner to drop other work in progress and work on this stakeholder’s requirement as the top-priority item.


C.

Share the prioritized items that the team is working on with the stakeholder and invite them to join the sprint planning session.


D.

Secure some additional funding to recruit more resources to the project team to enable faster delivery.


Expert Solution
Questions # 444:

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

Options:

A.

Schedule a meeting with the previous project manager


B.

Submit a change request to the change control board (CCB)


C.

Schedule training for project team members


D.

Conduct an earned value analysis (EVA)


Expert Solution
Questions # 445:

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

Options:

A.

Rebaseline the project schedule to show the current status of the project.


B.

Create a benefits management plan mapped to the organization's strategic objectives


C.

Perform a project cost-benefit analysis for the stakeholders


D.

Update the deliverables map against the agreed-upon project requirements


Expert Solution
Questions # 446:

A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?

Options:

A.

Contact the functional managers to request substitutes for the conflicting team members.


B.

Send a warning to both team members indicating that if the issue continues, both will be removed from the project.


C.

Schedule a meeting with both team members to understand the issue and facilitate a solution that satisfies both parties.


D.

Escalate both team members to their respective functional managers and let them take the appropriate actions


Expert Solution
Questions # 447:

An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?

Options:

A.

Provide feedback to the team and conduct a meeting to review the team rules.


B.

Provide feedback to the team and conduct a retrospective meeting to find a root cause.


C.

Provide feedback to the team and request agile training for the new member.


D.

Provide feedback to the team and coach the new team member in agile methodology.


Expert Solution
Questions # 448:

During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.

What should the project manager do first?

Options:

A.

Communicate the problem to the sponsor to force the key member to be maintained on the project.


B.

Initiate a change request and replace the key member as soon as possible.


C.

Explain to the company the importance of maintaining the key member on the project according to the vision of the project.


D.

Evaluate the impact of the key team member's removal from the project, look for alternatives, and submit a change request if required.


Expert Solution
Questions # 449:

A company is leading a project to develop a new product using an agile approach. A supplier was contracted to provide a solution for one of the product features based on mandatory scope, stable requirements, and fixed-price contract. During a meeting with the supplier, the project manager was informed that the company's business analyst also asked the supplier to add a solution for another feature as part of their deliverable.

What should the project manager do?

Options:

A.

Add the feature to the supplier's requirement list so they can deliver it.


B.

Ask the supplier to accommodate the additional scope under the current agreement.


C.

Ensure the project team understands the agreement and contract in place with the supplier.


D.

Monitor the work the business analyst is performing to avoid scope creep.


Expert Solution
Questions # 450:

Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?

Options:

A.

Reaffirm the required project obligations directly with the team member. oy


B.

Ask the team member to explain the reason for the absences.


C.

Assess the impact of the team member's absence on the task involved.


D.

Send a formal letter to the team member stating that their absences are noted.


Expert Solution