Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 433 Topic 44 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 433 Topic 44 Discussion

PMP Exam Topic 44 Question 433 Discussion:
Question #: 433
Topic #: 44

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?


A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline


B.

Motivate project team members by offering incentives to complete the project on time


C.

Describe to the team members how specific tools and techniques can be used to finish on time


D.

Convince team members to use a specific methodology to complete the project on time


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.