During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?
A.
Reevaluate the project schedule as the velocity will be impacted by the loss of resources
B.
Reevaluate the backlog priority with the product owner since the velocity has been impacted
C.
Reevaluate the scope of the current iteration to keep the same velocity and timeline
D.
Reevaluate the velocity as the iteration duration will be impacted by new requirements
In Agile project management, when a resource is lost and new requirements are added to the backlog, the project manager should reevaluate the backlog priority with the product owner. This is because the velocity, or the amount of work the team can handle in a given iteration, has been impacted. The project manager and the product owner need to reassess the priorities in the backlog to ensure that the most valuable items are being worked on given the current capacity of the team12. References:
Agile Project Management: What Is It and Why Does It Matter?1
Agile Project Manager Roles and Responsibilities: A Career Guide2
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit