PMI Project Management Professional (2025 Version) PMP Question # 433 Topic 44 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 433 Topic 44 Discussion

PMP Exam Topic 44 Question 433 Discussion:
Question #: 433
Topic #: 44

During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?


A.

Reevaluate the project schedule as the velocity will be impacted by the loss of resources


B.

Reevaluate the backlog priority with the product owner since the velocity has been impacted


C.

Reevaluate the scope of the current iteration to keep the same velocity and timeline


D.

Reevaluate the velocity as the iteration duration will be impacted by new requirements


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.