Question #: 434
Topic #: 44

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?


A.

Ask the team to collect the knowledge locally and share it at the end of the project.


B.

Utilize the cloud wiki to collect the necessary knowledge.


C.

Coordinate with the team and the project stakeholders to collect the knowledge.


D.

Provide just-in-time knowledge to the client, upon request.