PMI Project Management Professional (2025 Version) PMP Question # 408 Topic 41 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 408 Topic 41 Discussion

PMP Exam Topic 41 Question 408 Discussion:
Question #: 408
Topic #: 41

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?


A.

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.


B.

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.


C.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.


D.

Create a record in the issue register and escalate the issue to the project steering committee.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.