Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 408 Topic 41 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 408 Topic 41 Discussion

PMP Exam Topic 41 Question 408 Discussion:
Question #: 408
Topic #: 41

A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?


A.

Add the new stakeholder to the communications management plan


B.

Share the project status reports with the new stakeholder.


C.

Update the stakeholder engagement plan


D.

Schedule a meeting with the new stakeholder


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.