Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 404 Topic 41 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 404 Topic 41 Discussion

PMP Exam Topic 41 Question 404 Discussion:
Question #: 404
Topic #: 41

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.

What should the project manager do?


A.

Ask the human resources director to appoint a senior team leader


B.

Inform the project sponsor about the possible delay


C.

Directly manage the project team to avoid project delays


D.

Provide mentoring to the newly appointed team leader


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.