PMI Project Management Professional (2025 Version) PMP Question # 404 Topic 41 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 404 Topic 41 Discussion

PMP Exam Topic 41 Question 404 Discussion:
Question #: 404
Topic #: 41

A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?


A.

The product owner does not have visibility into what the team has done in the product increment.


B.

The product owner trusts the team and is marking the product as complete.


C.

The product owner has evaluated the product against the definition of done (DoD).


D.

The product owner will release the product to customers without showing them a demo.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.