Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 402 Topic 41 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 402 Topic 41 Discussion

PMP Exam Topic 41 Question 402 Discussion:
Question #: 402
Topic #: 41

A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase

How should the business increase the value of the project?


A.

Quantify the expected tangible and intangible benefits in the benefits management plan for each phase


B.

Ask the benefits owner to reassess the identified risks that are impacting the outcomes of the financial benefits.


C.

Consult with experts on methods to reduce costs and increase the financial value of the project


D.

Use a fishbone diagram to find the root cause of the lower financial benefits with the benefits owner


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.