PMI Project Management Professional (2025 Version) PMP Question # 402 Topic 41 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 402 Topic 41 Discussion

PMP Exam Topic 41 Question 402 Discussion:
Question #: 402
Topic #: 41

A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.

What should the project manager do?


A.

Use the existing budget for executing the fallback plan and update the baseline.


B.

Add additional resources to the project to fast track certain activities and reduce delays.


C.

Evaluate the fallback plan proposed by the team and submit a change request, if required.


D.

Communicate the delay to stakeholders and maintain the existing budget baseline.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.