Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 403 Topic 41 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 403 Topic 41 Discussion

PMP Exam Topic 41 Question 403 Discussion:
Question #: 403
Topic #: 41

A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches

What should the project manager do about the development team's request"?


A.

Escalate the request for additional financial resources


B.

Forward the request to the project management office (PMO) to amend the organizational process assets


C.

Ask the project sponsor to obtain approval for implementation of the new approach


D.

Analyze the requirements that will need to be addressed under the requested method


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.