PMI Project Management Professional (2025 Version) PMP Question # 403 Topic 41 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 403 Topic 41 Discussion

PMP Exam Topic 41 Question 403 Discussion:
Question #: 403
Topic #: 41

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?


A.

The project is over budget and behind schedule.


B.

The project is under budget and on schedule.


C.

The project is under budget and behind schedule.


D.

The project is on budget and on schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.