A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?


A.

Prioritize other items for the team and deal with the conflicting requirements later.


B.

Allow the project team to decide what is the most appropriate requirement to follow.


C.

Escalate to the project management office (PMO) and request a solution for the requirements.


D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.