Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 401 Topic 41 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 401 Topic 41 Discussion

PMP Exam Topic 41 Question 401 Discussion:
Question #: 401
Topic #: 41

In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.

What should the project manager do next1?


A.

Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder


B.

Inform the project sponsor that there are stakeholders who are not included in the communications management plan


C.

Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan


D.

Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.