PMI Project Management Professional (2025 Version) PMP Question # 414 Topic 42 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 414 Topic 42 Discussion

PMP Exam Topic 42 Question 414 Discussion:
Question #: 414
Topic #: 42

A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?


A.

Convene an impact analysis meeting.


B.

Escalate the issue to the product owner.


C.

Consult the communications management plan.


D.

Review the stakeholder register.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.