Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 414 Topic 42 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 414 Topic 42 Discussion

PMP Exam Topic 42 Question 414 Discussion:
Question #: 414
Topic #: 42

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?


A.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones


B.

Create a reward system granting incentives to the team members who are able to catch more defects


C.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.


D.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.