PMP Exam Topic 42 Question 416 Discussion:
Question #: 416
Topic #: 42

A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company

What should the project manager have the Scrum team do to recover from these issues?


A.

Review constraints in the ongoing sprint planning and evaluate options for the release plan


B.

Stop the sprint and replan and prioritize the backlog to reduce resource levels


C.

Consult the resource management plan for an appropriate response


D.

Continue with existing sprint plans to ensure some of the scope will be delivered