PMI Project Management Professional (2025 Version) PMP Question # 415 Topic 42 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 415 Topic 42 Discussion

PMP Exam Topic 42 Question 415 Discussion:
Question #: 415
Topic #: 42

A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.

What should the project manager do in this situation?


A.

Assess the impact of the stakeholder and engage properly.


B.

Escalate the stakeholder issue to the project sponsor.


C.

Develop a specific communications strategy for this stakeholder.


D.

Use interpersonal skills to gain stakeholder engagement.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.