PMI Project Management Professional (PMBOK 7th Version) PMP Question # 415 Topic 42 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 415 Topic 42 Discussion

PMP Exam Topic 42 Question 415 Discussion:
Question #: 415
Topic #: 42

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change

What should the project manager have done to avoid this situation?


A.

Requested that the sponsor approved the change request first.


B.

Assessed the change's overall impact to the project before submission


C.

Ensured that the change request was aligned with the project scope


D.

Submitted the change request directly to the CCB